Breakspear Road South Northbound Lane Closure Update

Due to earlier than anticipated completion of the trial hole surveys on Breakspear Road South, we have been able to remove the northbound lane closure for the remainder of this week and over the weekend. Work will commence on the installation of the hoarding on Monday 26th March and the northbound lane closure will be re-introduced from 7am on that day. This will operate until the 30th March.

A two way traffic light system will be in operation with the phasing of the lights being manually operated at peak times (07:00 – 10:00 and 15:00 – 18:00) to ensure that traffic continues to flow. We apologise for any inconvenience this will cause.

Posted on 23rd March 2018

by HS2 in Hillingdon