Gas Main Diversions at Harvil Road

To prepare for the construction of the new railway, we are working to move a large gas main. We will be digging trenches to install the gas main's new pipeline between the existing pipeline north of the Chiltern Mainline to a location south of the Dogs Trust.

These works will not impact local gas supplies. Work will start in April 2019 and is expected to be completed by November 2019. For more information please see the notification which is being sent to local residents .

Posted on 25th March 2019

by HS2 in Hillingdon