Celadine Way diversion:
Our works have progressed to a stage where we need to close and divert the Celandine Way. This temporary change will divert along the recently updated U43 footpath and utilise the new crossing point over Breakspear Road South. These works will start week commencing 13 September 2021.
For further information please see our works notification.
Utility investigations on West End Road:
We wrote to you recently to advise you that we would be carrying out ground investigation works from 10 to 20 August 2021. However, we need to reschedule these activities which will now take place from 1 6 to 28 August 2021 .
For further information please see our update works notification.