HS2 Works notification: Upcoming works at our sites on Harvil Road and Newyears Green Lane, 2 August to 22 December 2021

Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new bridge over the Chiltern Line railway, the Copthall tunnel and the conveyor system.

From 2 August 2021 , we will be carrying out the following activities:

  • Piling works for the west portal of the Copthall tunnel
  • Installation of the conveyor bridge over Newyears Green Lane
  • Installation of support structures (abutments and wingwalls) for the new bridge over the Chiltern Line railway
  • Sheet piling at the MSD buildings off Breakspear Road South
  • We will continue to monitor noise, dust and vibration throughout our works and ensure that adequate measures are in place to minimise disruption.

    For further information and detail of locations please see our works notification.

    If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk .

    Posted on 19th July 2021