HS2 Works Notification: Update on gas pipeline diversion near Harvil Road, September to November 2019

We are continuing our work to divert a gas main off Harvil Road. In order to ensure the work is complete by November 2019 when the pipeline is due to be operational, we need to extend our working hours at the Cadent Gas site to the west of Harvil Road.

We will be working 7am to 7pm, Monday to Sunday from September until November 2019. No noisy work will take place before 10 am on Sundays. These works will not impact local gas supplies.

For more information please see the works notification by clicking here .

Posted on 9th September 2019

by HS2 in Hillingdon