As part of the preparation works for the construction of HS2 we will be continuing to carry out some initial works in your area which will help us develop our plans for construction.
Ground Investigations
HS2 will be carrying out ground investigations work next to the railway line in Ruislip in three locations from early January 2020.
This involves drilling down to retrieve a small core of the ground. To do this we use drilling rigs which are small enough to be towed by an off-road vehicle.
The first site will be in Ruislip Rugby Club, from 6 January for up to four weeks.
The second site will be in Bridgewater Road Recreation Ground from 20 January for up to four weeks. This is a change of date from a previous notice.
The third site will be West Ruislip Car Park from 6 January for up to four weeks.
Further details can be found in the attached notifications:
Utility Surveys
We also need to conduct surveys of the utility services in the Ruislip area across five locations.
Scanning equipment will be used to create a map of the utility services below ground and they will be marked using biodegradable spray paint. We will use cameras to take site photos of the work completed.
The first site will be in Bridgewater Road, South Ruislip from 6 January.
The second site will be on Long Lane and station Approach from 6 January.
The third site will be on Ickenham Road from 6 January.
The forth site will be in the Great Central Avenue area from 6 January.
The fifth site will be in the West End Road area from 6 January.
All of these locations will last for a short period of time for short periods across a three month period.
Further details can be found in the attached notifications: