Update on gas main diversion works in Harefield

Work has been underway to move two gas pipelines in the Harefield area, to facilitate HS2’s construction and to continue to ensure a safe and reliable gas supply to the area.

Cadent has now successfully completed the diversion for the first of these pipelines, and has ceased work over winter.

Cadent will need to return to the northern site off Harvil Road next year to complete the second diversion.

We don’t yet have the details for when this work will be carried out, but we’ll make sure people are aware in advance.

In the meantime, you may see other work being carried out on behalf of HS2 around Harvil Road. For more information please see the notification sent to residents here .

Please contact us if you want to find out more.

Posted on 13th December 2019

by HS2 in Hillingdon