Update: Road closure of Breakspear Road South

Further to our update of 6 July 2018, whilst carrying out work to divert the water pipeline, Affinity Water have encountered some unexpected services within the carriageway which has required deeper excavations. The consequence of this is a delay to completing the works. We therefore need to extend the works to Friday 17 August 2018 and the closure of Breakspear Road South will remain in place until this date. We apologise for any inconvenience this will cause.

A high resolution map of traffic diversions can be found here.

Posted on 10th August 2018

by HS2 In Hillingdon